Project Description: |
TAUNTON- INTERSECTION IMPROVEMENTS AT WINTHROP STREET (ROUTE 44) AND HIGHLAND STREET
The proposed scope of work will include the following: traffic signal reconstruction, new crosswalks across on all intersection approaches, roadway widening for bicycle accommodation, (on-road bicycle lanes, buffered bicycle lanes, and SUP to be evaluated), sidewalk and curb ramp reconstruction, new pavement markings, and warning/regulatory signing, stormwater improvements and utility pole relocations.
|
Location: |
|
Design Responsibility: | Municipality |
Right of Way Responsibility: | Municipality |
Construction Begins: | Autumn 2030 |
Project Manager: | Anni H Autio![]() |
Estimated Total Contract Cost: | $2,216,000.00 |
Estimated Total Federal Participating Construction Cost: | $2,458,900.00 |
Funding Provision: | This project is planned to be funded through the 2030 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization. |
District: | District 5 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges |
|
|
|