Project Description:
GARDNER- SHARED-USE PATH CONSTRUCTION, NORTH CENTRAL PATHWAY EXTENSION
The project includes development of a 10-foot wide paved shared use path, with two-foot gravel shoulders, beginning on the former railbed near its intersection with Jackson Street, and continuing approximately 1.6 miles north to Green Street / Route 140.
Location:
  • City of Gardner
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Project Manager: Joseph Gyujong Yoo
    Estimated Total Contract Cost: $4,680,000.00
    Estimated Total Federal Participating Construction Cost: $5,070,000.00
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/19/2023
    Project Need Form PNF Approved 04/11/2023
    Project Initiation Form PIF Entered 04/19/2023
    Project Initiation Form PIF Approved 04/19/2023
    Project Initiation Form PRC Submitted 04/19/2023
    Project Review Committee PRC Approved 06/01/2023
    Project Management