| Project Description:
|
ATTLEBORO- FOXBOROUGH- MANSFIELD- NORTH ATTLEBORO- SYSTEMATIC BRIDGE PRESERVATION AT 12 BRIDGES ALONG THE I-95 CORRIDOR
|
| Location:
|
City of Attleboro
Town of Foxborough
Town of Mansfield
Town of North Attleborough
|
| Design Responsibility:
|
In-House Boston |
| Right of Way Responsibility:
|
MassDOT |
| Construction Begins:
|
Spring 2028 |
| Project Manager:
|
Albin Napit |
| Estimated Total Contract Cost:
|
$8,484,800.00 |
| Estimated Total Federal Participating Construction Cost:
|
N/A |
| District:
|
District 5 |
| Current Status:
|
This project is in the preliminary design phase. |