Project Description: |
ATTLEBORO- NORTH ATTLEBORO- SYSTEMATIC BRIDGE PRESERVATION AT 5 BRIDGES ALONG THE I-95 CORRIDOR
The project is a bridge preservation job addressing bridges in the I-95 corridor. The five bridges to be repaired will be in the towns of Attleboro and North Attleboro. A combination of deck, superstructure, and substructure repairs will be conducted to restore the bridges to a state of good repair.
|
Location: |
|
Design Responsibility: | In-House Boston |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Spring 2028 |
Project Manager: | Alyson Bedard |
Estimated Total Contract Cost: | $7,222,500.00 |
Estimated Total Federal Participating Construction Cost: | $7,490,000.00 |
Funding Provision: | This project is planned to be funded through the 2028 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization. |
District: | District 5 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges
|
|
|
|