Project Description:
FOXBORO- BRIDGE PRESERVATION AT 6 BRIDGES ALONG THE I-95 CORRIDOR
Location:
  • Town of Foxborough
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2026
    Project Manager: Albin Napit
    Estimated Total Contract Cost: $4,914,000.00
    Estimated Total Federal Participating Construction Cost: $5,278,000.00
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: FOXBOROUGH
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $4,222,400.00
    State Cost: $1,055,600.00
    Total Cost: $5,278,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/20/2023
    Project Need Form PNF Approved 04/20/2023
    Project Initiation Form PIF Entered 04/20/2023
    Project Initiation Form PIF Approved 04/20/2023
    Project Initiation Form PRC Submitted 04/21/2023
    Project Review Committee PRC Approved 06/01/2023
    Project Management