Project Description:
BEVERLY- BURLINGTON- DANVERS- GLOUCESTER- WOBURN- BRIDGE PRESERVATION AT 9 BRIDGES CARRYING STATE ROUTE 128
This project will include repairs of concrete frame structures carrying state Route 128 over the following roads: Route 97 and Route 1A/Dodge Street in Beverly; South Bedford Street in Burlington; Route 35/High Street and Route 62/Elliot Street in Danvers; Route 133/Essex Ave in Gloucester; and Forest Park Road in Woburn.
Location:
  • City of Beverly
  • Town of Burlington
  • Town of Danvers
  • City of Gloucester
  • City of Woburn
  • Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2027
    Project Manager: Alyson Bedard
    Estimated Total Contract Cost: $14,715,000.00
    Estimated Total Federal Participating Construction Cost: $15,260,000.00
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: BEVERLY
    BURLINGTON
    DANVERS
    GLOUCESTER
    WOBURN
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $13,184,640.00
    State Cost: $3,296,160.00
    Total Cost: $16,480,800.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/20/2023
    Project Need Form PNF Approved 04/20/2023
    Project Initiation Form PIF Entered 04/20/2023
    Project Initiation Form PIF Approved 04/20/2023
    Project Initiation Form PRC Submitted 04/21/2023
    Project Review Committee PRC Approved 06/01/2023
    Project Management