Project Description: |
STOUGHTON- INTERSECTION IMPROVEMENTS AT ROUTE 27 (PARK STREET) AND TURNPIKE STREET
Work on this project will include geometric, safety and traffic operational improvements at the intersection of Park Street and Turnpike Street. The proposed design incorporates turning lanes on all approaches; geometric improvements that will provide a shorter crossing distance to minimize pedestrian exposure; bicycle accommodations; a new sidewalk along the northwest side of Turnpike Street and a Shared Use Path along the southeast side up to Campanelli Parkway.
|
Location: |
|
Design Responsibility: | Municipality |
Construction Begins: | Spring 2029 |
Project Manager: | Joseph Gyujong Yoo |
Estimated Total Contract Cost: | $3,032,414.75 |
Estimated Total Federal Participating Construction Cost: | $3,264,123.25 |
Funding Provision: | This project is planned to be funded through the 2029 Transportation Improvement Program for the Old Colony Metropolitan Planning Organization. |
District: | District 5 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges |
|
|
|