Project Description:
STOUGHTON- INTERSECTION IMPROVEMENTS AT ROUTE 27 (PARK STREET) AND TURNPIKE STREET
Work on this project will include geometric, safety and traffic operational improvements at the intersection of Park Street and Turnpike Street. The proposed design incorporates turning lanes on all approaches; geometric improvements that will provide a shorter crossing distance to minimize pedestrian exposure; bicycle accommodations; a new sidewalk along the northwest side of Turnpike Street and a Shared Use Path along the southeast side up to Campanelli Parkway.
Location:
  • Town of Stoughton
  • Design Responsibility: Municipality
    Construction Begins: Spring 2029
    Project Manager: Joseph Gyujong Yoo
    Estimated Total Contract Cost: $3,032,414.75
    Estimated Total Federal Participating Construction Cost: $3,264,123.25
    Funding Provision: This project is planned to be funded through the 2029 Transportation Improvement Program for the Old Colony Metropolitan Planning Organization.
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2029
    Responsible MPO: Old Colony Metropolitan Planning Organization
    Location: Municipality
    Cities: STOUGHTON
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $3,029,106.40
    State Cost: $757,276.60
    Total Cost: $3,786,383.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/21/2023
    Project Need Form PNF Approved 04/19/2023
    Project Initiation Form PIF Entered 04/21/2023
    Project Initiation Form PIF Approved 04/21/2023
    Project Initiation Form PRC Submitted 04/21/2023
    Project Review Committee PRC Approved 06/01/2023
    Project Management