Project Description: |
BOSTON- DEDHAM- INTERSECTION IMPROVEMENTS AT VFW PARKWAY AND SPRING STREET
This project will reconstruct the intersections at VFW Parkway and Spring Street in Boston and at Bridge Street, Needham Street, and Riverside Drive in Dedham. New bicycle accommodation will be added on Bridge Street.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Project Manager: | Lawrence Cash |
Estimated Total Contract Cost: | $4,920,867.50 |
Estimated Total Federal Participating Construction Cost: | $5,357,253.50 |
District: | District 6 |
Current Status: | This project is in the preliminary design phase. |
|