AUBURN- BRIDGE REPLACEMENT, A-17-050 (4KH), BANCROFT STREET OVER I-90
This project will consist of a full bridge replacement at the Bancroft street bridge over the I-90 roadway in the town of Auburn. The project will also evaluate the bridge substructure for potential rehabilitation/reuse.
Location:
  • Town of Auburn
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2029
    Project Manager: Caitlin A Marshall
    Estimated Total Contract Cost: $37,950,000.00
    Estimated Total Federal Participating Construction Cost: $39,675,000.00
    Funding Provision: This project is planned to be funded through the 2029 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2029
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: AUBURN
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $46,023,000, Design Status = Approved, YOE = 16%
  • Category FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    Federal Cost: $1,600,000.00
    State Cost: $400,000.00
    Total Cost: $2,000,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/21/2023
    Project Need Form PNF Approved 04/18/2023
    Project Initiation Form PIF Entered 04/21/2023
    Project Initiation Form PIF Approved 04/21/2023
    Project Initiation Form PRC Submitted 04/21/2023
    Project Review Committee PRC Approved 06/01/2023