Project Description: |
BRIDGEWATER- BRIDGE REHABILITATION, B-23-001 (44H), VERNON STREET OVER TAUNTON RIVER
This project will consist of a bridge rehabilitation at the Vernon street bridge over the Taunton River in the town of Auburn. The scope of the project is primarily replacement of the bridge superstructure.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | Municipality |
Construction Begins: | Spring 2029 |
Project Manager: | Anthony Christakis |
Estimated Total Contract Cost: | $19,876,995.00 |
Estimated Total Federal Participating Construction Cost: | $20,613,180.00 |
Funding Provision: | This project is planned to be funded through the 2029 Transportation Improvement Program for the Old Colony Metropolitan Planning Organization. |
District: | District 5 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges
|
|
|
|