BRIDGEWATER- BRIDGE REHABILITATION, B-23-001 (44H), VERNON STREET OVER TAUNTON RIVER
This project will consist of a bridge rehabilitation at the Vernon street bridge over the Taunton River in the town of Auburn. The scope of the project is primarily replacement of the bridge superstructure.
Location:
  • Town of Bridgewater
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2029
    Project Manager: Anthony Christakis
    Estimated Total Contract Cost: $19,876,995.00
    Estimated Total Federal Participating Construction Cost: $20,613,180.00
    Funding Provision: This project is planned to be funded through the 2029 Transportation Improvement Program for the Old Colony Metropolitan Planning Organization.
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2029
    Responsible MPO: Old Colony Metropolitan Planning Organization
    Location: Municipality
    Cities: BRIDGEWATER
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

  • amended via STIP Action 2
  • Category FA - Bridge Formula Program - Local Off System Bridge
    Federal Cost: $21,425,706.00
    State Cost: $0.00
    Total Cost: $21,425,706.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/21/2023
    Project Need Form PNF Approved 04/18/2023
    Project Initiation Form PIF Entered 04/21/2023
    Project Initiation Form PIF Approved 04/21/2023
    Project Initiation Form PRC Submitted 04/21/2023
    Project Review Committee PRC Approved 06/01/2023