Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BRIDGEWATER- BRIDGE REHABILITATION, B-23-001 (44H), VERNON STREET OVER TAUNTON RIVER
This project will consist of a bridge rehabilitation at the Vernon street bridge over the Taunton River in the town of Auburn. The scope of the project is primarily replacement of the bridge superstructure.
Location:
  • Town of Bridgewater
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2029
    Project Manager: Anthony Christakis
    Estimated Total Contract Cost: $19,876,995.00
    Estimated Total Federal Participating Construction Cost: $20,613,180.00
    Funding Provision: This project is planned to be funded through the 2029 Transportation Improvement Program for the Old Colony Metropolitan Planning Organization.
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2029
    Responsible MPO: Old Colony Metropolitan Planning Organization
    Location: Municipality
    Cities: BRIDGEWATER
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Bridge Formula Program - Local Off System Bridge
    Federal Cost: $23,911,289.00
    State Cost: $0.00
    Total Cost: $23,911,289.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/21/2023
    Project Need Form PNF Approved 04/18/2023
    Project Initiation Form PIF Entered 04/21/2023
    Project Initiation Form PIF Approved 04/21/2023
    Project Initiation Form PRC Submitted 04/21/2023
    Project Review Committee PRC Approved 06/01/2023
    Project Management