Project Description:
NEW BRAINTREE- BRIDGE REHABILITATION, N-07-004 (185), BARR ROAD OVER MEADOW BROOK
This project will consist of a bridge rehabilitation at the Barr Road bridge over the Meadow Brook in the town of New Braintree. The scope of the project is primarily replacement of the bridge superstructure.
Location:
  • Town of New Braintree
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Autumn 2029
    Project Manager: Janhavi Limaye
    Estimated Total Contract Cost: $9,450,000.00
    Estimated Total Federal Participating Construction Cost: $9,800,000.00
    Funding Provision: This project is planned to be funded through the 2029 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 2
    Current Status: The Notice to Proceed to begin work on the contract has been issued (as of 04/26/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2029
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: NEW BRAINTREE
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $11,368,000, Design Status = Approved, YOE = 16%
  • Category FA - Bridge Formula Program - Local Off System Bridge
    Federal Cost: $11,368,000.00
    State Cost: $0.00
    Total Cost: $11,368,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/21/2023
    Project Need Form PNF Approved 04/18/2023
    Project Initiation Form PIF Entered 04/21/2023
    Project Initiation Form PIF Approved 04/21/2023
    Project Initiation Form PRC Submitted 04/21/2023
    Project Review Committee PRC Approved 06/01/2023
    Project Management
    Consultant Contract Process NTP Issued 04/26/2024