| Project Description: |
NEW BRAINTREE- BRIDGE REHABILITATION, N-07-004 (185), BARR ROAD OVER MEADOW BROOK
This project will consist of a bridge rehabilitation at the Barr Road bridge over the Meadow Brook in the town of New Braintree. The scope of the project is primarily replacement of the bridge superstructure.
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | Municipality |
| Construction Begins: | Autumn 2029 |
| Project Manager: | Janhavi Limaye![]() |
| Estimated Total Contract Cost: | $9,450,000.00 |
| Estimated Total Federal Participating Construction Cost: | $9,800,000.00 |
| Funding Provision: | This project is planned to be funded through the 2029 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization. |
| District: | District 2 |
| Current Status: | The Notice to Proceed to begin work on the contract has been issued (as of 04/26/2024 ) |
|
Bridges
|
||||||
|
|
|||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||