Project Description:
HINSDALE- BRIDGE REPLACEMENT, H-16-001 (04V), MAPLE STREET OVER EAST BRANCH HOUSATONIC RIVER
This project will consist of a full bridge replacement at the Maple Street bridge over the East branch of the Housatonic River, in the town of Hinsdale. The project will also evaluate the bridge substructure for potential rehabilitation/reuse.
Location:
  • Town of Hinsdale
  • Right of Way Responsibility: Municipality
    Construction Begins: Summer 2029
    Project Manager: Kathy Dougherty
    Estimated Total Contract Cost: $3,740,000.00
    Estimated Total Federal Participating Construction Cost: $4,080,000.00
    Funding Provision: This project is planned to be funded through the 2029 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2029
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: HINSDALE
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    Federal Cost: $3,786,240.00
    State Cost: $946,560.00
    Total Cost: $4,732,800.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/21/2023
    Project Need Form PNF Approved 04/18/2023
    Project Initiation Form PIF Entered 04/21/2023
    Project Initiation Form PIF Approved 04/21/2023
    Project Initiation Form PRC Submitted 04/21/2023
    Project Review Committee PRC Approved 06/01/2023
    Project Management