Project Description:
GREENFIELD- DECK REPLACEMENT, G-12-022 (144), LOG PLAIN ROAD WEST OVER G&W RAILROAD
This project will consist of a bridge deck replacement at the Log Plain Road West bridge over the G&W Railroad in the town of Greenfield. The project will also involve cleaning and painting of the structural steel.
Location:
  • Town of Greenfield
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2026
    Project Manager: Muazzez G Reardon
    Estimated Total Contract Cost: $5,605,429.00
    Estimated Total Federal Participating Construction Cost: $5,997,648.50
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Franklin Regional Council of Governments.
    District: District 2
    Current Status: Design Public Hearing (as of 10/30/2025 )

    Contracts (1) Progress
    # 115773 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Franklin Regional Council of Governments
    Location: Municipality
    Cities: GREENFIELD
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    Federal Cost: $3,955,248.00
    State Cost: $988,812.00
    Total Cost: $4,944,060.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/21/2023
    Project Need Form PNF Approved 04/18/2023
    Project Initiation Form PIF Entered 04/21/2023
    Project Initiation Form PIF Approved 04/21/2023
    Project Initiation Form PRC Submitted 04/21/2023
    Project Review Committee PRC Approved 06/01/2023
    Project Management
    100% Design 100% Package Received 08/25/2025
    100% Design 100% Package Comments to DE 09/25/2025
    25% Design 25% Package Received 07/16/2024
    25% Design 25% Package Comments to DE 08/13/2024
    25% Design Design Public Hearing 10/30/2025
    75% Design 75% Package Received 04/29/2025
    75% Design 75% Package Comments to DE 05/28/2025