LEE- BRIDGE REPLACEMENT, L-05-008 (05B), SILVER STREET OVER GREENWATER BROOK
Location:
  • Town of Lee
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Project Manager: Douglas Johnson
    Estimated Total Federal Participating Construction Cost: N/A
    Funding Provision: This project is planned to be funded through the 2029 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    • L05008 
    See the Milestone Details tab for additional Project information
    Planned Federal FY: 2029
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: LEE
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Bridge Formula Program - Local Off System Bridge
    Federal Cost: $8,212,714.00
    State Cost: $0.00
    Total Cost: $8,212,714.00