Project Description:
ORANGE- BRIDGE REPLACEMENT, O-03-015 (14X), BROOKSIDE ROAD OVER G&W RAILROAD
This project will consist of a full bridge replacement at the Brookside Road bridge over the G&W Railroad, in the Town of Orange.
Location:
  • Town of Orange
  • Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2028
    Project Manager: Adam W Kiel
    Estimated Total Contract Cost: $8,423,874.70
    Estimated Total Federal Participating Construction Cost: $8,965,200.80
    Funding Provision: This project is planned to be funded through the 2028 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 2
    Current Status: 25% Package Received (as of 07/02/2025 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2028
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: ORANGE
    Category: Design and Force Agreements
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • added via STIP Action 4.
  • Category FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    Federal Cost: $7,745,933.60
    State Cost: $1,936,483.40
    Total Cost: $9,682,417.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/24/2023
    Project Need Form PNF Approved 04/23/2023
    Project Initiation Form PIF Entered 04/24/2023
    Project Initiation Form PIF Approved 04/24/2023
    Project Initiation Form PRC Submitted 04/24/2023
    Project Review Committee PRC Approved 06/01/2023
    Project Management
    25% Design 25% Package Received 07/02/2025
    Consultant Contract Process NTP Issued 06/05/2024