Project Description:
GLOUCESTER- BRIDGE REHABILITATION, G-05-015 (326), CENTENNIAL AVE OVER MBTA
This project will consist of bridge rehabilitation at the Centennial Ave bridge over the MBTA railroad in Gloucester. The timber superstructure will be replaced and the bridge substructure will be rehabilitated.
Location:
  • City of Gloucester
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Joseph Gyujong Yoo
    Estimated Total Contract Cost: $2,484,337.50
    Estimated Total Federal Participating Construction Cost: $2,668,362.50
    District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/24/2023
    Project Need Form PNF Approved 04/24/2023
    Project Initiation Form PIF Entered 04/24/2023
    Project Initiation Form PIF Approved 04/24/2023
    Project Initiation Form PRC Submitted 05/10/2023
    Project Review Committee PRC Approved 06/01/2023