Project Description:
WORCESTER- BICYCLE AND PEDESTRIAN IMPROVEMENTS ON MILLBURY STREET
Location:
  • City of Worcester
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2031
    Project Manager: Yaseen Al Abdullah
    Estimated Total Contract Cost: $1,931,863.10
    Estimated Total Federal Participating Construction Cost: $2,129,493.70
    Funding Provision: This project is planned to be funded through the 2031 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3
    Current Status: 25% Package Received (as of 04/27/2026 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2031
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: WORCESTER
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $3,854,255, Design Status = Approved, YOE = 16%, PM Score = 15 out of 27.
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $3,083,404.00
    State Cost: $770,851.00
    Total Cost: $3,854,255.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/25/2023
    Project Need Form PNF Approved 04/14/2023
    Project Initiation Form PIF Entered 04/25/2023
    Project Initiation Form PIF Approved 04/25/2023
    Project Initiation Form PRC Submitted 04/25/2023
    Project Review Committee PRC Approved 06/01/2023
    Project Management
    25% Design 25% Package Received 04/27/2026
    Consultant Contract Process NTP Issued 01/12/2024