| Project Description: |
HOLYOKE- WEST SPRINGFIELD- INTERSTATE PAVEMENT PRESERVATION AND RELATED WORK ON I-91
|
| Location: |
|
| Design Responsibility: | In-House Boston |
| Right of Way Responsibility: | MassDOT |
| Construction Begins: | Spring 2028 |
| Project Manager: | Koby J Lemrise![]() |
| Estimated Total Contract Cost: | $13,382,273.40 |
| Estimated Total Federal Participating Construction Cost: | $13,633,608.60 |
| Funding Provision: | This project is planned to be funded through the 2028 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization. |
| District: | District 2 |
| Current Status: | 75% Package Received (as of 01/12/2026 ) |
|
Bridges |
||||||
|
|
||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||