Project Description:
NEWTON- BRIDGE SUBSTRUCTURE REPAIRS AND RELATED WORK, N-12-019, LEWIS TERRACE AND N-12-021, WALNUT STREET OVER I-90 AND CSX/MBTA RAILROAD
Location:
  • City of Newton
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2024
    Project Manager: Alina Daragan
    Estimated Total Contract Cost: $2,015,404.50
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 6
    Current Status: This project has been advertised for construction bids. (as of 04/20/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/10/2023
    Project Need Form PNF Approved 05/10/2023
    Project Initiation Form PIF Entered 05/10/2023
    Project Initiation Form PIF Approved 05/10/2023
    Project Initiation Form PRC Submitted 05/10/2023
    Project Review Committee PRC Approved 05/12/2023
    Project Status Advertised 04/20/2024
    Project Management
    100% Design 100% Package Received 12/21/2023
    100% Design 100% Package Comments to DE 01/26/2024
    Final Design PS&E Received 02/13/2024
    Final Design PS&E Received - Resub 1 03/01/2024