Project Description:
DISTRICT 6- SCHEDULED & EMERGENCY FIRE LINE, STANDPIPE, AND HYDRANT REPAIRS AND IMPROVEMENTS AT VARIOUS LOCATIONS
Project would create an open contract for fire line, standpipe, and hydrant repair and maintenance.
Location:
Design Responsibility: In-House Boston
Right of Way Responsibility: MassDOT
Construction Begins: Summer 2024
Project Manager: Ancarlos M Youssef
Estimated Total Contract Cost: $482,609.00
Estimated Total Federal Participating Construction Cost: N/A
District: District 6
Current Status: This project has been advertised for construction bids. (as of 03/23/2024 )

Contracts (0) Progress
No contracts associated with this project

Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/10/2023
    Project Need Form PNF Approved 05/10/2023
    Project Initiation Form PIF Entered 05/10/2023
    Project Initiation Form PIF Approved 05/10/2023
    Project Initiation Form PRC Submitted 05/10/2023
    Project Review Committee PRC Approved 05/15/2023
    Project Status Advertised 03/23/2024
    Project Management
    100% Design 100% Package Received 01/17/2024
    Final Design PS&E Received 02/01/2024
    Final Design PS&E to FAPRO 02/12/2024