Project Description:
STOUGHTON- CORRIDOR IMPROVEMENTS ON ROUTE 138, FROM CANTON T.L. TO CHARLES AVENUE (PHASE 2)
The project will include mill and overlay, new and reconstructed sidewalks on one side between Canton TL and York Street; south of York Street sidewalks on both sides, buffered bike lanes, ADA compliant curb ramps, and signs and pavement markings.
Location:
  • Town of Stoughton
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2025
    Project Manager: Shahpar Negah
    Estimated Total Contract Cost: $7,989,440.01
    Estimated Total Federal Participating Construction Cost: $9,206,819.78
    District: District 5
    Current Status: PS&E Received (as of 12/19/2023 )

    Contracts (1) Progress
    # 115784 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/12/2023
    Project Need Form PNF Approved 05/09/2023
    Project Initiation Form PIF Entered 05/12/2023
    Project Initiation Form PIF Approved 05/12/2023
    Project Initiation Form PRC Submitted 05/12/2023
    Project Review Committee PRC Approved 06/01/2023
    Project Management
    Final Design PS&E Received 12/19/2023