Project Description:
WESTBOROUGH- FISHER STREET IMPROVEMENTS (SRTS)
The project includes reconstruction of an existing sidewalk, construction of new ADA-compliant sidewalk ramps, and installation of updated signs and pavement markings to facilitate students walking along Fisher Street to the Gibbons Middle School and Armstrong Elementary School.
Location:
  • Town of Westborough
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Autumn 2027
    Project Manager: Aidee Cira
    Estimated Total Contract Cost: $2,684,361.75
    Estimated Total Federal Participating Construction Cost: $2,927,592.25
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3
    Current Status: The Notice to Proceed to begin work on the contract has been issued (as of 07/22/2024 )

    Contracts (1) Progress
    # 115759 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: WESTBOROUGH
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $2,114,100, Design Status = Approved, YOE = 8%
  • Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $1,691,280.00
    State Cost: $422,820.00
    Total Cost: $2,114,100.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/15/2023
    Project Need Form PNF Approved 05/05/2023
    Project Initiation Form PIF Entered 05/15/2023
    Project Initiation Form PIF Approved 05/10/2023
    Project Initiation Form PRC Submitted 05/15/2023
    Project Review Committee PRC Approved 06/01/2023
    Project Management
    Consultant Contract Process NTP Issued 07/22/2024