| Project Description: |
FAIRHAVEN- NEW BEDFORD- INTERSTATE PAVEMENT PRESERVATION AND RELATED WORK ON I-195
This project proposes to preserve the open-graded friction course on I-195 in Fairhaven and New Bedford.
|
| Location: |
|
| Design Responsibility: | In-House Boston |
| Right of Way Responsibility: | MassDOT |
| Construction Begins: | Autumn 2030 |
| Project Manager: | Koby J Lemrise![]() |
| Estimated Total Contract Cost: | $13,552,000.00 |
| Estimated Total Federal Participating Construction Cost: | $14,168,000.00 |
| Funding Provision: | This project is planned to be funded through the 2030 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization. |
| District: | District 5 |
| Current Status: | This project is in the preliminary design phase. |
|
Bridges |
||||||
|
|
||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||