Project Description:
BELLINGHAM- MEDWAY- MILFORD- INTERSTATE PAVEMENT PRESERVATION AND RELATED WORK ON I-495
This project proposes to preserve the open-graded friction course on I-495 in Bellingham, Medway, and Milford.
Location:
  • Town of Bellingham
  • Town of Medway
  • Town of Milford
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: Koby J Lemrise
    Estimated Total Contract Cost: $18,480,000.00
    Estimated Total Federal Participating Construction Cost: $19,320,000.00
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/19/2023
    Project Need Form PNF Approved 05/19/2023
    Project Initiation Form PIF Entered 05/19/2023
    Project Initiation Form PIF Approved 05/19/2023
    Project Initiation Form PRC Submitted 05/24/2023
    Project Review Committee PRC Approved 06/01/2023
    Project Management