| Project Description: |
DISTRICT 3- SCHEDULED AND EMERGENCY BRIDGE DECK AND JOINT REPAIRS AT VARIOUS LOCATIONS ON I-90
The scope of this contract consists of scheduled and emergency deck and joint repairs on I-90 bridges.
|
| Location: | |
| Construction Begins: | Autumn 2023 |
| Resident Engineer: | Ryan Johnson![]() |
| Construction Bid Price: | $2,237,675.00 |
| District: | District 3 |
|
Bridges |
||||||||
|
||||||||||
|
|
|
|||||||||||||||||||||||||||||||||||