Project Description:
DISTRICT 3- SCHEDULED AND EMERGENCY RESURFACING AND RELATED WORK AT VARIOUS LOCATIONS
This project consists of resurfacing various locations throughout District 3 as part of the Municipal Paving Program. More information on the program can be found at the following website: https://www.mass.gov/municipal-pavement-program. The pavement work to be done primarily includes one of the following operations: • 2± inches of pavement fine milling, placing 1± inch of Superpave Leveling Course, where required, and 2 inches of Superpave Surface Course • Full depth pavement reclamation with emulsified asphalt stabilization Safety improvements and incidental work shall occur at all locations where resurfacing is performed.
Location:
Construction Begins: Summer 2024
Resident Engineer: Anthony Tavalone
Construction Bid Price: $5,888,934.00
District: District 3

Contracts (1) Progress
# 125315 -- Construction Contract
Scheduled and Emergency Resurfacing and Related Work at Various Locations Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/01/2024
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Maintenance
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/05/2023
    Project Initiation Form PIF Entered 06/26/2023
    Project Initiation Form PRC Submitted 06/26/2023
    Project Review Committee PRC Approved 07/05/2023
    Project Status Advertised 02/24/2024
    Project Management
    100% Design 100% Package Received 12/11/2023
    Final Design PS&E Received 12/11/2023
    Final Design PS&E to FAPRO 02/15/2024