BOSTON- BRIDGE PRESERVATION, B-16-234 (BKV), RICHMOND STREET OVER STATE ROUTE 1A
This project will consist of bridge preservation items at the Richmond Street bridge over State Route 1A Northbound, in the city of Boston. This includes repaving, repairing abutment cracks, repairing beams and lighting, and replacing sidewalks.
Location:
  • City of Boston
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Alyson Bedard
    Estimated Total Contract Cost: $496,074.55
    Estimated Total Federal Participating Construction Cost: $562,240.63
    District: District 6
    Current Status: 100% Package Comments to DE (as of 11/21/2023 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/26/2023
    Project Need Form PNF Approved 06/23/2023
    Project Initiation Form PIF Entered 06/26/2023
    Project Initiation Form PIF Approved 06/26/2023
    Project Initiation Form PRC Submitted 06/27/2023
    Project Review Committee PRC Approved 07/06/2023
    Project Management
    100% Design 100% Package Received 10/23/2023
    100% Design 100% Package Comments to DE 11/21/2023