Project Description:
ARLINGTON- LEXINGTON- SCHEDULED SUBSTRUCTURE REPAIRS L-10-017, L-10-020, A-10-020, A-10-012
The purpose of this project is to provide substructure repairs to the bridges carrying Pleasant Street, Park Avenue, Spring Street and Watertown Street over Route 2. The Work will include but not be limited to: 1) Removing the deteriorated concrete from any element of the substructure, including but not limited to pier caps, pier columns, wing walls, backwalls, breastwalls and abutments. 2) Jacking and shoring to support pier caps and/or various beams over piers and abutments may be required to allow concrete repairs to the substructure. 3) Replacing excavated, spalled, delaminated, or deteriorated concrete, and replacing any broken, missing or deteriorated reinforcing steel with new material. 4) Replacing missing or damaged granite or cement concrete slope paving, either in kind or with cement concrete slope paving where needed and as directed by the Engineer.
Location:
  • Town of Arlington
  • Town of Lexington
  • Construction Begins: Autumn 2024
    Resident Engineer: Lokman Arran
    Construction Bid Price: $1,222,716.00
    District: District 4

    Contracts (1) Progress
    # 128032 -- Construction Contract
    Scheduled Substructure Repairs L-10-017, L-10-020, A-10-020, A-10-012

    Bridges

    Contract Dates
    Notice to Proceed: 11/05/2024
    Contract Information
    Project Designer: In-House Boston
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/27/2023
    Project Initiation Form PIF Entered 06/27/2023
    Project Initiation Form PRC Submitted 07/19/2023
    Project Review Committee PRC Approved 08/09/2023
    Project Status Advertised 09/07/2024
    Project Management
    100% Design 100% Package Received 06/20/2024
    100% Design 100% Package Comments to DE 07/11/2024
    75% Design 75% Package Received 04/23/2024
    75% Design 75% Package Comments to DE 05/20/2024
    Final Design PS&E Received 08/14/2024
    Final Design PS&E Received - Resub 1 08/27/2024