Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
NEWTON- IMPROVEMENTS AT PARKER STREET FOR THE OAK HILL MIDDLE SCHOOL (SRTS)
This project will implement bike and pedestrian safety improvements at the Parker Rd and Route 9 intersection in support of students at the Oak Hill and Brown Middle Schools, Bowen Elementary School, and Newton South High School.
Location:
  • City of Newton
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2027
    Project Manager: Joseph Gyujong Yoo
    Estimated Total Contract Cost: $1,252,191.50
    Estimated Total Federal Participating Construction Cost: $1,381,637.50
    District: District 6
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/27/2023
    Project Need Form PNF Approved 05/22/2023
    Project Initiation Form PIF Entered 06/27/2023
    Project Initiation Form PIF Approved 06/06/2023
    Project Initiation Form PRC Submitted 06/27/2023
    Project Review Committee PRC Approved 07/13/2023
    Project Management