| Project Description: |
HOLLISTON- LINDEN STREET IMPROVEMENTS AT ROBERT ADAMS MIDDLE SCHOOL (SRTS)
The project includes installing new and reconstructing existing sidewalks along Linden Street adding a new crosswalk constructing ADA accessible ramps and installing a pedestrian warning flasher assembly at Linden Street around Grove Street and Avon Street.
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | Municipality |
| Construction Begins: | Spring 2029 |
| Project Manager: | Yaseen Al Abdullah![]() |
| Estimated Total Contract Cost: | $1,078,294.75 |
| Estimated Total Federal Participating Construction Cost: | $1,226,421.94 |
| Funding Provision: | This project is planned to be funded through the 2029 Transportation Improvement Program for the Boston Metropolitan Planning Organization. |
| District: | District 3 |
| Current Status: | 25% Package Comments to DE (as of 09/30/2026 ) |
|
Bridges |
||||||
|
|
||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||