Project Description: |
HOLLISTON- LINDEN STREET IMPROVEMENTS AT ROBERT ADAMS MIDDLE SCHOOL (SRTS)
The project includes installing new and reconstructing existing sidewalks along Linden Street adding a new crosswalk constructing ADA accessible ramps and installing a pedestrian warning flasher assembly at Linden Street around Grove Street and Avon Street.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | Municipality |
Construction Begins: | Summer 2027 |
Project Manager: | Yaseen Al Abdullah |
Estimated Total Contract Cost: | $843,750.00 |
Estimated Total Federal Participating Construction Cost: | $937,500.00 |
Funding Provision: | This project is planned to be funded through the 2027 Transportation Improvement Program for the Boston Metropolitan Planning Organization. |
District: | District 3 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges |
|
|
|