Project Description:
WAREHAM- BRIDGE PRESERVATION, W-06-037 (4AJ) & W-06-040 (4AD), MAPLE SPRINGS ROAD AND TIHONET ROAD OVER STATE ROUTE 25
This project will consist of a bridge preservation at the Maple Springs Road and Tihonet Road bridges over State Route 25, in the town of Wareham. The work proposed includes steel beam end repairs, full painting, joint repairs, and minor deck & substructure patching.
Location:
  • Town of Wareham
  • Construction Begins: Winter 2023/2024
    Resident Engineer: Michael Horton
    Construction Bid Price: $4,607,165.00
    District: District 5
    Current Status: Prime Coatings has completed all Intermediate/Finish Painting at Tihonet Rd bridge (except for steel repair locations). Prime has completed blasting/priming for 75% of Maple Springs Rd Bridge locations and is halfway complete with Intermediate/finish coats. Prime will look to re-mobilize in March to continue with bridge painting operations. NEL Corp will also look to mobilize to complete steel repairs in March/April. Scheduled work hours are Sunday through Thursday 8PM to 5AM Expect Periodic lane closures and restrictions (as of 03/05/2026)
    Additional Info: Gannett Fleming is on-site conducting third party paint inspections. Temporarily de-mobilized. (as of 03/05/2026)

    Contracts (1) Progress
    # 124619 -- Construction Contract
    Bridge Preservation, W-06-037 (4AJ) & W-06-040 (4AD), Maple Springs Road and Tihonet Road over State Route 25 75% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 01/23/2024
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/07/2023
    Project Need Form PNF Approved 07/07/2023
    Project Initiation Form PIF Entered 07/07/2023
    Project Initiation Form PIF Approved 07/07/2023
    Project Initiation Form PRC Submitted 07/07/2023
    Project Review Committee PRC Approved 07/13/2023
    Project Status Advertised 11/11/2023
    Project Management
    100% Design 100% Package Received 08/31/2023
    100% Design 100% Package Comments to DE 09/18/2023
    Final Design PS&E Received 10/06/2023
    Final Design PS&E to FAPRO 10/30/2023