| Project Description: | 
 GREAT BARRINGTON- BRIDGE REPLACEMENT, G-11-008 (04K), BROOKSIDE ROAD OVER HOUSATONIC RIVER 
This project will consist of bridge replacement at the Brookside Road bridge over the Housatonic River in the town of Great Barrington. The proposed work includes stringer & abutment replacements, steel repairs, deck & joint improvements, paving, and cleaning & painting.  
 | 
| Location: | 
 | 
| Design Responsibility: | Consultant | 
| Right of Way Responsibility: | MassDOT | 
| Construction Begins: | Autumn 2030 | 
| Project Manager: | Dongke  Yu![]()  | 
| Estimated Total Contract Cost: | $48,249,250.00 | 
| Estimated Total Federal Participating Construction Cost: | $50,523,375.00 | 
| Funding Provision: | This project is planned to be funded through the 2030 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization. | 
| District: | District 1 | 
| Current Status: | This project is in the preliminary design phase. | 
  | 