Project Description: |
DEERFIELD- CULVERT REPLACEMENT ON ROUTE 10 BY INTERSECTION OF WAPPING ROAD/DEPOT ROAD AND ROUTE 10
The project aims to replace an undersized culvert on Route 10 that is causing erosion of the side slope and flooding of the roadway.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Summer 2029 |
Project Manager: | Adetoyin Ayoola Olaoye |
Estimated Total Contract Cost: | $1,756,250.00 |
Estimated Total Federal Participating Construction Cost: | $1,889,437.50 |
Funding Provision: | This project is planned to be funded through the 2029 Transportation Improvement Program for the Franklin Regional Council of Governments. |
District: | District 2 |
Current Status: | This project is in the preliminary design phase. |
|