Project Description: |
PALMER- SUPERSTRUCTURE REPLACEMENT, P-01-052 (4MD & 4ME) AND P-01-055 (4M9 & 4MA), I-90 EB/WB OVER THORNDIKE STREET AND ROUTE 67
This project will consist of superstructure replacements and bearing repairs/replacements at the I-90 Eastbound and Westbound bridges over Thorndike Street and Route 67, in the town of Palmer.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Project Manager: | Christopher I Cameron |
Estimated Total Contract Cost: | $32,200,000.00 |
Estimated Total Federal Participating Construction Cost: | N/A |
District: | District 2 |
Current Status: | This project is in the preliminary design phase. |
|