Project Description:
BRIMFIELD- DECK REPLACEMENT, B-24-061 (4KW & 4KX), I-90 EB/WB OVER WASHINGTON/RR/RIVER
This project will consist of a bridge deck replacement at the I-90 EB/WB bridge over the Quaboag River, railroad tracks, and Washington Road, in the town of Brimfield. The bridges will also undergo bearing repair/replacement and cleaning & painting of structural steel.
Location:
  • Town of Brimfield
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2029
    Project Manager: Jonathan E Freeman
    Estimated Total Contract Cost: $3,528,000.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 2
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/01/2023
    Project Need Form PNF Approved 08/29/2023
    Project Initiation Form PIF Entered 09/01/2023
    Project Initiation Form PIF Approved 09/01/2023
    Project Initiation Form PRC Submitted 09/22/2023
    Project Review Committee PRC Approved 10/12/2023