Project Description: |
ADAMS- SUPERSTRUCTURE REPLACEMENT, A-04-017 (02W), COOK STREET OVER HOOSIC RIVER
This project consists of deck replacement at the Cook Street bridge over the Hoosic River, in the town of Adams. In addition, the bridge will be evaluated for potential superstructure replacement, with preservation/repairs to substructure as needed.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | Municipality |
Project Manager: | Dongke Yu |
Estimated Total Contract Cost: | $5,875,200.00 |
Estimated Total Federal Participating Construction Cost: | $6,310,400.00 |
District: | District 1 |
Current Status: | This project is in the preliminary design phase. |
|