Project Description:
GREENFIELD- BICYCLE AND PEDESTRIAN IMPROVEMENTS ON ROUTE 2A
The project is a proposed shared used path along the north side of Route 2A that connects 2 existing projects, one west and one east of the limits of work: 608414 INTERSECTION IMPROVEMENTS AT TWO LOCATIONS, ROUTE 2 AND COLRAIN ROAD & ROUTE 2 AND BIG Y ENTRANCE and 612509 BRIDGE REPLACEMENT, G-12-007, LOWER MAIN STREET (SR 2A) OVER GREEN RIVER respectively. The project also completes a gap in the bicycle and pedestrian planned network that connects further east to Greenfield town center through a complete streets project 610921 DOWNTOWN COMPLETE STREETS IMPROVEMENTS ON MAIN STREET (ROUTE 2A).
Location:
  • Town of Greenfield
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Stephanie Upson
    Estimated Total Contract Cost: $3,612,500.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 2
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/20/2023
    Project Need Form PNF Approved 08/21/2023
    Project Initiation Form PIF Entered 09/20/2023
    Project Initiation Form PIF Approved 09/20/2023
    Project Initiation Form PRC Submitted 09/20/2023
    Project Review Committee PRC Approved 10/12/2023
    Project Management