| Project Description: |
NEEDHAM- NEWTON- BRIDGE REPLACEMENT ON CHRISTINA STREET
Project aims to replace the dilapidated Christina Street railroad bridge over the Charles River between Newton and Needham with a modern bridge carrying a shared use path.
|
| Location: |
|
| Design Responsibility: | Municipality |
| Right of Way Responsibility: | Municipality |
| Project Manager: | Janhavi Limaye![]() |
| Estimated Total Contract Cost: | $4,468,750.00 |
| Estimated Total Federal Participating Construction Cost: | $4,785,787.50 |
| District: | District 6 |
| Current Status: | This project is in the preliminary design phase. |
|
Bridges |
||||||
|
|
|
||||||||||||||||||||||||||