Project Description: |
NANTUCKET- INTERSECTION IMPROVEMENTS ON MILESTONE ROAD AT NOBADEER FARM ROAD
The Nobadeer Farm Road approach to this intersection experienced failing level of service based on a 2017 traffic study and is an a 2015-2017 HSIP Cluster. In addition, modernization improvements to the bus stops, bicycle, and pedestrian facilities are needed.
|
Location: |
|
Design Responsibility: | Consultant |
Project Manager: | Greg Frazier![]() |
Estimated Total Contract Cost: | $6,232,500.00 |
Estimated Total Federal Participating Construction Cost: | $6,916,275.00 |
District: | District 5 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges |
|
|
|