Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
MIDDLEBOROUGH- INTERSECTION IMPROVEMENTS ON ROUTE 28 AT MERCHANT'S WAY AND WILLIAMS PLACE
The purpose of this project is to address safety concerns at the intersection of Route 28 at Merchant's Way and Williams Place. The higher volumes on Route 28 vs. those on the side streets do not allow for many gaps for vehicles to enter Route 28. Under the current unsignalized condition, these entry movements are problematic. There is also a need for multi modal accommodations at this intersection. Work on this project will include the installation of a traffic control signal (a roundabout will also be evaluated through the ICE process). The traffic signal installation will include ADA compliant pedestrian equipment, crosswalks, and curb ramps. Turn lanes on Route 28 will be evaluated for potential improvements. The project will also include bicycle and pedestrian accommodations within the project limits to address safety and accessibility. The sidewalks will be reconstructed on the north side of Route 28 and a shared use path is proposed on the south side of Route 28.
Location:
  • Town of Middleborough
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2029
    Project Manager: Greg Frazier
    Estimated Total Contract Cost: $9,695,000.00
    Estimated Total Federal Participating Construction Cost: $10,400,075.00
    Funding Provision: This project is planned to be funded through the 2029 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization.
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2029
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: MIDDLEBOROUGH
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $10,857,678.30
    State Cost: $1,206,408.70
    Total Cost: $12,064,087.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/22/2023
    Project Need Form PNF Approved 09/20/2023
    Project Initiation Form PIF Entered 09/22/2023
    Project Initiation Form PIF Approved 09/22/2023
    Project Initiation Form PRC Submitted 10/06/2023
    Project Review Committee PRC Approved 10/12/2023
    Project Management