NANTUCKET- ROUNDABOUT RECONSTRUCTION AT MILESTONE ROAD, ORANGE STREET, SPARKS AVENUE AND OLD SOUTH ROAD
The project proposes to reconstruct the Milestone Rotary at the intersection of Milestone Road, Sparks Avenue, Orange Street and Old South Road in Nantucket into a modern roundabout. In addition to congestion issues, the intersection is a 2008-2017 HSIP Bicycle Crash Cluster. The pedestrian and bicycle accommodations will be brought into conformance with design standards and the bus stops will be evaluated within the project.
Location:
  • Town of Nantucket
  • Design Responsibility: Consultant
    Construction Begins: Summer 2031
    Project Manager: Greg Frazier
    Estimated Total Contract Cost: $5,833,961.10
    Estimated Total Federal Participating Construction Cost: $6,474,011.70
    Funding Provision: This project is planned to be funded through the 2031 Transportation Improvement Program for the Nantucket Planning and Economic Development Commission.
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2031
    Responsible MPO: Nantucket Planning and Economic Development Commission
    Location: Municipality
    Cities: NANTUCKET
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $6,758,868.60
    State Cost: $750,985.40
    Total Cost: $7,509,854.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/22/2023
    Project Need Form PNF Approved 09/18/2023
    Project Initiation Form PIF Entered 09/22/2023
    Project Initiation Form PIF Approved 09/22/2023
    Project Initiation Form PRC Submitted 10/06/2023
    Project Review Committee PRC Approved 10/12/2023