Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
HANOVER- INTERSECTION IMPROVEMENTS AT COLUMBIA ROAD (ROUTE 53/139) AND BROADWAY
Location:
  • Town of Hanover
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2029
    Project Manager: Jonathan E Freeman
    Estimated Total Contract Cost: $5,580,000.00
    Estimated Total Federal Participating Construction Cost: $5,938,600.00
    Funding Provision: This project is planned to be funded through the 2029 Transportation Improvement Program for the Old Colony Metropolitan Planning Organization.
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2029
    Responsible MPO: Old Colony Metropolitan Planning Organization
    Location: Municipality
    Cities: HANOVER
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $6,199,898.40
    State Cost: $688,877.60
    Total Cost: $6,888,776.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/25/2023
    Project Need Form PNF Approved 09/22/2023
    Project Initiation Form PIF Entered 09/25/2023
    Project Initiation Form PIF Approved 09/25/2023
    Project Initiation Form PRC Submitted 10/03/2023
    Project Review Committee PRC Approved 10/12/2023
    Project Management