Project Description:
DISTRICT 5- VRU SYSTEMIC SAFETY PROJECT NEAR BUS STOPS
MassDOT’s Vulnerable Road User (VRU) Assessment found that a disproportional amount of pedestrian and bicyclist fatal or serious injury crashes occurred within 300 feet of a bus stop. In an effort to address this, MassDOT is investing Highway Safety Improvement Program (HSIP) funds into crossing improvements at bus stops throughout the state in a multi-year approach. Bus stops that were identified as high risk for pedestrians or had a high potential for people walking within 300 feet of them were prioritized for these improvements. Project elements include adding pedestrian refuge islands, installing flashing warning signs (RRFBs) or other signs, painting high-visibility crosswalks, curb extensions, etc. Locations are currently identified in the following locations and subject to change: Bourne, Brockton, Edgartown, Falmouth, Tisbury, and West Tisbury.
Location:
  • Town of Bourne
  • City of Brockton
  • Town of Edgartown
  • Town of Falmouth
  • Town of Tisbury
  • Town of West Tisbury
  • Construction Begins: Spring 2025
    Resident Engineer: Alfredo Nunez
    Construction Bid Price: $1,454,684.70
    District: District 5
    Current Status: • The Pre-Construction Meeting was held on 5/28/25. • Contract submittals started to be received on 5/28/25. • The Survey crew completed marking Brockton location on 7/7/25. • The Survey crew traveled to Martha’s Vineyard to mark locations on 9/15/25. • Advanced warning signs were installed for Bourne and Falmouth locations on 9/23 & 9/24/25. • Tree protection was installed in Falmouth on 10/3/25. • Sawcutting roadway was done in Bourne on 10/6/25. • Erosion control and tree trimming was finished in Bourne on 10/14/25. • Meeting in Martha’s Vineyard between Construction, Projects and the Contractor (for RFIs) was held on 10/15/25. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM (as of 10/22/2025)

    Contracts (1) Progress
    # 129541 -- Construction Contract
    VRU Systemic Safety Project near Bus Stops 38% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/24/2025
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/03/2023
    Project Need Form PNF Approved 09/19/2023
    Project Initiation Form PIF Entered 10/03/2023
    Project Initiation Form PIF Approved 09/19/2023
    Project Initiation Form PRC Submitted 10/03/2023
    Project Review Committee PRC Approved 10/12/2023
    Project Status Advertised 02/22/2025
    Project Management
    100% Design 100% Package Received 07/03/2024
    100% Design 100% Package Comments to DE 08/05/2024
    25% Design 25% Package Received 03/26/2024
    75% Design 75% Package Received 03/26/2024
    75% Design 75% Package Comments to DE 04/29/2024
    Final Design PS&E Received 10/11/2024
    Final Design PS&E Received - Resub 1 12/05/2024