Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 4- DISTRICT 6- VRU SYSTEMIC SAFETY PROJECT NEAR BUS STOPS
MassDOT’s Vulnerable Road User (VRU) Assessment found that a disproportional amount of pedestrian and bicyclist fatal or serious injury crashes occurred within 300 feet of a bus stop. In an effort to address this, MassDOT is investing Highway Safety Improvement Program (HSIP) funds into crossing improvements at bus stops throughout the state in a multi-year approach. Bus stops that were identified as high risk for pedestrians or had a high potential for people walking within 300 feet of them were prioritized for these improvements. Project elements include adding pedestrian refuge islands, installing flashing warning signs (RRFBs) or other signs, painting high-visibility crosswalks, curb extensions, etc. Locations are currently identified in the following locations and subject to change: Lawrence, Lowell, Medford, North Andover, Tewksbury, Braintree, Milton, and Weymouth.
Location:
  • Town of Braintree
  • City of Lawrence
  • City of Lowell
  • Town of Milton
  • Town of North Andover
  • Town of Tewksbury
  • Town of Weymouth
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2025
    Project Manager: Koby J Lemrise
    Estimated Total Contract Cost: $1,851,755.77
    Estimated Total Federal Participating Construction Cost: $1,962,536.36
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the STATEWIDE.
    District: District 4
    Current Status: This project has been advertised for construction bids. (as of 02/22/2025 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: STATEWIDE
    Location: District
    Districts: District 4
    District 6
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • Added via STIP Action 5.
  • Category FA - Hwy Safety Improvement Prgm - Vulnerable User Safety / VUS
    Federal Cost: $1,567,701.00
    State Cost: $174,189.00
    Total Cost: $1,741,890.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/03/2023
    Project Need Form PNF Approved 09/19/2023
    Project Initiation Form PIF Entered 10/03/2023
    Project Initiation Form PIF Approved 09/19/2023
    Project Initiation Form PRC Submitted 10/03/2023
    Project Review Committee PRC Approved 10/12/2023
    Project Status Advertised 02/22/2025
    Project Management
    100% Design 100% Package Received 07/02/2024
    100% Design 100% Package Comments to DE 08/05/2024
    25% Design 25% Package Received 03/19/2024
    75% Design 75% Package Received 03/19/2024
    75% Design 75% Package Comments to DE 04/22/2024
    Final Design PS&E Received 09/12/2024
    Final Design PS&E Received - Resub 1 11/25/2024