Project Description:
DISTRICT 4- DISTRICT 6- VRU SYSTEMIC SAFETY PROJECT NEAR BUS STOPS
MassDOT’s Vulnerable Road User (VRU) Assessment found that a disproportional amount of pedestrian and bicyclist fatal or serious injury crashes occurred within 300 feet of a bus stop. In an effort to address this, MassDOT is investing Highway Safety Improvement Program (HSIP) funds into crossing improvements at bus stops throughout the state in a multi-year approach. Bus stops that were identified as high risk for pedestrians or had a high potential for people walking within 300 feet of them were prioritized for these improvements. Project elements include adding pedestrian refuge islands, installing flashing warning signs (RRFBs) or other signs, painting high-visibility crosswalks, curb extensions, etc. Locations are currently identified in the following locations and subject to change: Andover, Billerica, Burlington, Chelmsford, Everett, Lawrence, Lowell, Medford, Merrimac, Methuen, North Andover, Revere, and Tewksbury.
Location:
Design Responsibility: Consultant
Right of Way Responsibility: MassDOT
Project Manager: Koby J Lemrise
Estimated Total Contract Cost: $1,260,688.55
Estimated Total Federal Participating Construction Cost: $1,349,473.04
District: District 4
Current Status: 75% Package Received (as of 03/19/2024 )

Contracts (0) Progress
No contracts associated with this project

Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/03/2023
    Project Need Form PNF Approved 09/19/2023
    Project Initiation Form PIF Entered 10/03/2023
    Project Initiation Form PIF Approved 09/19/2023
    Project Initiation Form PRC Submitted 10/03/2023
    Project Review Committee PRC Approved 10/12/2023
    Project Management
    25% Design 25% Package Received 03/19/2024
    75% Design 75% Package Received 03/19/2024