Project Description:
BOSTON- SOMERVILLE- ELECTRICAL CABINET REPLACEMENTS ALONG I-90 AND I-93
The project includes the replacement of load centers along I-93 and sections of I-90, installation of new electrical cabinets, and service connections. The proposed work also consists of removal and disposal of existing equipment, wiring, and miscellaneous debris.
Location:
  • City of Boston
  • City of Somerville
  • Construction Begins: Autumn 2026
    Resident Engineer: Daniel Stiven
    Construction Bid Price: $3,773,773.00
    District: District 6

    Contracts (1) Progress
    # 135134 -- Construction Contract
    Electrical Cabinet Replacements along I-90 and I-93

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/08/2026
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/16/2023
    Project Need Form PNF Approved 09/22/2023
    Project Initiation Form PIF Entered 10/16/2023
    Project Initiation Form PIF Approved 09/22/2023
    Project Initiation Form PRC Submitted 10/16/2023
    Project Review Committee PRC Approved 10/17/2023
    Project Status Advertised 07/04/2026
    Project Management
    100% Design 100% Package Received 09/08/2025
    Final Design PS&E Received 04/13/2026
    Final Design PS&E to FAPRO 06/24/2026
    Final Design PS&E Received - Resub 1 06/11/2026