| Project Description: |
BOSTON- TUNNEL SAFETY IMPROVEMENTS, EMERGENCY EXIT SIGNAGE AND EGRESS ROUTE UPDATES AT MHS TUNNELS
The work of this project will consist of replacing existing emergency exit signage and egress route delineation with new enhanced signage and delineation.
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | MassDOT |
| Construction Begins: | Spring 2027 |
| Project Manager: | Hema P Bhatt![]() |
| Estimated Total Contract Cost: | $22,031,635.40 |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 6 |
| Current Status: | 25% Package Comments to DE (as of 05/02/2026 ) |
|
Bridges |
||||||
|
|
|
||||||||||||||||||||||||||||||||