| Project Description: |
BOSTON- TUNNEL PRESERVATION, OVERHEAD CONCRETE REPAIRS AT MHS TUNNELS
The work under this project will consist of repairing deteriorated overhead concrete within the MHS tunnel system on a priority basis.
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | MassDOT |
| Project Manager: | Hema P Bhatt![]() |
| Estimated Total Contract Cost: | $5,758,447.50 |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 6 |
| Current Status: | 25% Package Received (as of 05/03/2024 ) |
|
Bridges |
||||||
|
|
|
|||||||||||||||||||||||||||||