Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOSTON- TUNNEL PRESERVATION, TUNNEL LEAK SEALING/FIREPROOFING AND MISCELLANEOUS REPAIRS AT MHS TUNNELS
The work under this project consists of inspection maintenance and repair of elements of the Central Artery/Tunnel system. The majority of the work is related to the control of leaking elements of the tunnels and repairs or maintenance to those elements that are deteriorated as a result of the leakage. Elements of the tunnel to be repaired or receive maintenance include slurry walls, roadway barriers, roadway wearing surfaces, girders, soldier piles, coating systems, etc.
Location:
  • City of Boston
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2027
    Project Manager: Hema P Bhatt
    Estimated Total Contract Cost: $21,000,000.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 6
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/10/2023
    Project Need Form PNF Approved 11/10/2023
    Project Initiation Form PIF Entered 11/10/2023
    Project Initiation Form PIF Approved 11/10/2023
    Project Initiation Form PRC Submitted 11/24/2023
    Project Review Committee PRC Approved 12/14/2023
    Project Management