Project Description: |
SOMERVILLE- TUNNEL PRESERVATION, LIGHTING REPLACEMENT IN SOMERVILLE TUNNEL (STATE ROUTE 28 NB/FELLSWAY)
The work under this project consists of replacing the existing tunnel lighting in the Somerville Tunnel system, on State Route 28 NB/Fellsway.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Project Manager: | Hema P Bhatt |
Estimated Total Contract Cost: | $3,105,000.00 |
Estimated Total Federal Participating Construction Cost: | $3,335,000.00 |
District: | District 4 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges |
|
|
|