Project Description:
RAYNHAM- TAUNTON- BRIDGE REPLACEMENT, R-02-003=T-01-004 (3M4), SOUTH STREET EAST OVER THE TAUNTON RIVER
The proposed project consists of replacing the bridge deck, increasing safety, and improving operations of the roadway. Significant widening of the bridge is not part of this project, however a 5-foot bike lane on both sides of the bridge will be considered to facilitate pedestrian and bicyclist access.
Location:
  • Town of Raynham
  • City of Taunton
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Autumn 2026
    Project Manager: Herrio Lamothe
    Estimated Total Contract Cost: $6,913,567.34
    Estimated Total Federal Participating Construction Cost: $6,269,240.00
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization.
    District: District 5
    Current Status: 25% Package Received (as of 03/10/2025 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: RAYNHAM
    TAUNTON
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

  • Earmark MA 278 being used to fund this project.
  • Category FA - High Priority Projects (HPP)
    Federal Cost: $4,250,837.60
    State Cost: $1,062,709.40
    Total Cost: $5,313,547.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/17/2023
    Project Need Form PNF Approved 09/13/2023
    Project Initiation Form PIF Entered 11/17/2023
    Project Initiation Form PIF Approved 11/17/2023
    Project Initiation Form PRC Submitted 11/21/2023
    Project Review Committee PRC Approved 12/14/2023
    Project Management
    25% Design 25% Package Received 03/10/2025