Project Description: |
BLANDFORD- CULVERT REPLACEMENT, B-14-028, ROUTE 23 OVER POND BROOK
The purpose of this project is to completely replace the culvert and reconstruct the roadway approaches if necessary.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Project Manager: | Harry Adolphe |
Estimated Total Contract Cost: | $2,055,000.00 |
Estimated Total Federal Participating Construction Cost: | $2,243,100.00 |
District: | District 1 |
Current Status: | The Contract Scope of Work has been sent to the Design Engineer for consideration (as of 05/21/2024 ) |
|
Bridges |
|
|
|